What Was the Condition of This Roof Before Work Started?

The roof at 11663 Margate St in North Hollywood had reached the end of its useful life. The grey asphalt shingles were heavily weathered, with granule loss across multiple planes and visible curling along tab edges.
This kind of surface deterioration is exactly what happens when an asphalt shingle roof ages under Southern California’s relentless UV exposure. NOAA climate records show the Los Angeles Basin averages well over 280 sunny days per year, and that sustained solar loading breaks down the asphalt binder from the top down, sending granules into the gutters and leaving the mat exposed. Once the granule coating is gone in patches, the shingles stiffen, curl at the edges, and can no longer shed water reliably.
Project Gallery
A close look at the surface before tear-off confirmed the problem. The tabs were cupped and brittle, there were streaks across the field where biological growth had taken hold, and the color had faded to an uneven chalky grey. None of that was storm or hail damage. It was age and sun, compounded over many years on a low-pitched roof with broad, unshaded planes that catch heat all day. The homeowner’s goal was straightforward: a clean start, a solid new deck, and a shingle system that would perform reliably for years to come.
Roof Replacement Inc scheduled the initial site inspections across October 13 through 16, 2025, confirming scope and ordering materials before the crew mobilized for tear-off.
What Did the Tear-Off Reveal Underneath the Old Shingles?

Pulling the old shingles off exposed the original roof deck: wide wood boards laid with open gaps between them, the spaced sheathing construction typical of homes built in this part of Los Angeles decades ago. That decking could not support a modern shingle system without a solid substrate underneath it.
Spaced board sheathing was standard practice on older homes in the region. The boards allowed ventilation under wood shingles or early composition shingles, but the system was never designed to carry today’s architectural laminate products, which require continuous solid nailing surface. Beyond the structural concern, several boards showed darkening from years of moisture cycling through the gaps, and the ridge area had visible deterioration along one board edge.
The tear-off itself happened on October 16 and 17, 2025. The crew stripped the entire shingle field down to the bare wood boards, cleared all debris, and pulled the old nails. This is the step that reveals what a roof is actually working with beneath the surface layer. On this job, the exposed deck confirmed that re-sheathing was the right call: the boards were structurally sound enough to serve as a base layer, but the gaps between them ruled out direct application of underlayment and shingles.
When we strip a roof back to spaced board decking like this, the gap pattern tells a lot about the original construction era. These boards were laid for a wood shingle system, and what comes next has to treat them as a substrate rather than a finished deck.
How Was the New Deck Built?
New plywood panels were installed over the existing wood board sheathing, creating a continuous, nail-ready surface across the entire roof. That solid deck is the foundation every other layer depends on.
Plywood re-sheathing over old spaced boards is a proven method for bringing an aging deck up to current standards without a full structural overhaul. The new panels bridged the gaps in the original boards, eliminated any flex or unevenness in the nailing surface, and gave the underlayment and shingles a consistent substrate from eave to ridge. The re-sheathing work was completed on October 17, 2025, the same day the tear-off finished.

With the new plywood down, the crew moved to underlayment on October 19. California’s Title 24 building energy standards set minimum performance requirements for roofing assemblies, and using a quality synthetic underlayment is consistent with meeting those standards on a re-roof of this type. The product installed here was Owens Corning DeckDefense, a synthetic underlayment that is lighter and more tear-resistant than traditional felt, and that lays flat on the deck without the waviness that felt can develop in warm weather. The rolls are clearly printed "DECKDEFENSE" with the Owens Corning branding, visible in the gallery photos from the installation day.
Synthetic underlayment products like DeckDefense have become the standard on quality re-roofs across Southern California over the past several years because they handle the heat and UV exposure during the installation window far better than organic felt, which can degrade quickly if left exposed between trades. Once DeckDefense was rolled across the full deck and fastened, the roof was protected and ready for shingles.
Flashing, Chimneys, and Skylights
Two painted masonry chimneys and several skylights cut through the shingle field, and each one required new flashing set before shingles could go in around them. Penetration flashing is where most long-term leaks originate, so this work received close attention.
This home’s roof geometry is more complex than a simple two-plane gable. The low-pitched planes meet at several hips and valleys, and two masonry chimneys rise through the field, one mid-slope and one near a hip intersection. There are also multiple skylights set into the deck. Each of those penetrations is a potential water entry point if the flashing detail is not right.

New step flashing and counter-flashing were set at both chimneys, integrating with the new shingle courses as they were installed. The skylights received new flashing collars before the shingles were brought up around them. On re-roofs we almost always find the original flashing reused at the chimney, which is where the leak the homeowner called about actually starts. Replacing the flashing at the same time as the shingles eliminates that failure point entirely rather than leaving an old metal component in an otherwise new assembly.
The chimneys on this property are painted masonry, finished in white, and they stand prominently above the shingle field. Their condition was sound and their caps were intact, so no masonry repair was in scope. The focus was on the junction between the chimney base and the new roof surface, sealed with fresh step and counter-flashing that will move independently of the masonry as the structure expands and contracts through seasonal temperature swings. U.S. Census housing data shows a large share of Southern California’s single-family stock was built before 1980, meaning properties like this one routinely carry original penetration details that are well past their design life by the time a full re-roof is warranted.
Installing the New Shingle Field

New grey architectural asphalt shingles were installed starting at the eaves and worked up to the ridge, with hip and ridge cap shingles finishing every exposed corner. The completed field is consistent in color and alignment across all planes.
Architectural shingles, sometimes called dimensional or laminate shingles, are thicker than the three-tab products they replaced on most residential roofs. The layered construction creates shadow lines across the face of each shingle that give the finished field a textured appearance. On a broad low-pitched roof like this one, that texture reads clearly from street level and gives the home a finished, substantive look that flat three-tab products do not.
The crew began shingle installation on October 19 and completed the field on October 20, 2025. Courses were run parallel to the eaves with consistent exposure, and each shingle was fastened through the new plywood deck into the original boards below, giving the nails solid purchase through two layers of wood. Hip and ridge cap shingles were installed along every hip line and across the ridge, capping the field cleanly and sealing the most wind-exposed edges of the roof. All plumbing vents and the turbine vent were flashed and counter-flashed as the shingle courses came up around them.
The finished color is a mid-tone grey that reads as neutral against the painted chimneys and the existing stucco and trim on the home. It sits well within the range of colors common in this North Hollywood neighborhood, where many homes carry similar grey or charcoal shingle roofs.
The Finished Roof
The completed project delivered a fully re-sheathed, properly flashed, and newly shingled roof across all planes of the home. The photos taken on October 20, 2025 show a clean, uniform shingle field with tight courses, correctly finished hips, and new flashing visible at both chimneys and all skylight perimeters.
From the ridge looking back along the main slope, the alignment is consistent from eave to peak, and the hip caps follow the geometry of the roof cleanly down to the fascia line. The two white painted chimneys stand out against the grey field, and the skylight frames sit flush and sealed into the surrounding shingles. No exposed felt, no misaligned courses, no gaps at the penetrations.

This is what a re-roof done as a complete system looks like: new deck, new underlayment, new flashing, new shingles, all installed in the correct sequence so each layer protects the one beneath it. The work was performed by a contractor Licensed by the California Contractors State License Board (CSLB), which is the credential homeowners in California should confirm before any roofing work begins. The project ran from the first site inspection on October 13 through completion on October 20, 2025, a total span of 8 days from initial visit to finished roof.
If your North Hollywood home has a similarly aged roof showing granule loss, curling shingles, or any of the conditions visible in the before photos here, the right starting point is a proper inspection that looks at the deck condition, not just the surface. A roof that needs re-sheathing can still be re-roofed efficiently; the key is knowing about the deck before the job starts rather than after tear-off is underway.